Soil erosion mitigation plans ignored, waters from stream identified as main cause !


 

A drone picture of the collapsed beams along Jalan Tun Sardon leading to Balik Pulau on the left while Jalan Paya
Terubong on the right leads to Relau.— CHAN BOON KAI/The Star
(Above) A closer view of the collapsed beams. (Right) The affected section of the project overlooking Jalan Paya Terubong heading to Relau in the background.

https://content.jwplatform.com/players/Arqv95pp-dBiC3tzP.html

Tragic Situation: (Top) A landslide at the construction site in Jalan Bukit Kukus, Paya Terubong, caused four containers to be covered with mud – Bernama,  Closed call:(Right below) Survivors of the landslide surveying the scene

 Checks show projects did not follow SOP

GEORGE TOWN: As the search and rescue operation for seven buried foreign workers at a construction site in Paya Terubong is going on, shocking information has surfaced that not a single construction site in Penang is following the soil erosion mitigation plan stipulated in their project approvals.

The Star has learnt that the state government has launched Ops Lumpur shortly after the general election, requiring enforcement officers from the local councils to inspect and report on every construction site in all five districts in the state.

A consultant civil engineer familiar with Ops Lumpur claimed that every single construction project did not observe the soil erosion mitigation plan.

He said Ops Lumpur was overseen directly by state exco members and enforcement officers were required to visit the sites.

“Their reports shocked the state exco members. Every contractor failed to do soil erosion measures in every site.

“Now you know why streams near construction site are always yellow when it rains,” he said.

The consultant engineer said the state went after developers who claimed they were not aware and blamed the contractors.

“Civil engineers are often disgusted when they do site visits because it is common for us to see that the soil erosion mitigation plans are never followed,” he said.

The consultant said it was easy to inspect construction sites and check on the progress and questioned whether state government agencies regularly conducted scheduled and surprise visits.

“How often do they conduct spot checks? How strictly do they conduct enforcement rounds on construction sites? If we keep contractors on their toes all the time, we might not have so many landslides,” he said, referring to the latest landslide in Bukit Kukus, the site of a hillside highway from Paya Terubong to Bukit Jambul is being built.

A teh tarik-coloured stream was observed flowing between Jalan Paya Terubong and the barred entrance to the highway construction site yesterday.

It has been raining almost every day in Penang this week.

In yesterday’s incident, rescue team found one survivor and two dead bodies. At press time, seven are still missing.

The Fire and Rescue Department received a distress call about the landslide at 1.56pm.

An Indonesian worker who only wished to be known as Endo, 36, said three of his relatives from Sulawesi were trapped in the landslide and he was working in another nearby construction site.

“It rained all night (Thursday). The rain stopped at 9am (yesterday) and resumed at 1pm. At my site, all of us stayed in our quarters and didn’t work because of the rain.

“I got a call from others that my relatives are missing. So, now I’ll just wait,” he said.

Last Thursday, 14 concrete beams measuring 25m long each, crashed down from an elevated section of the highway.

No injuries were reported and a stop-work order was issued pending investigations of the collapse.

Chief Minister Chow Kon Yeow, who visited the site with several state exco members, said he reminded rescue workers to be wary while searching for the missing victims because the rain could have rendered the slopes unstable.

“All work has stopped here and the contractor was about to send in its report on the collapse of the concrete beams on Oct 11,” he said, adding that the place where the beams collapsed was far from the landslide. – The Star by arnold lohlo tern chern

Water from stream identified as main cause of landslide

GEORGE TOWN: Water flow from a stream on the hilly area in Jalan Bukit Kukus, Paya Terubong, near here has been identified as among the cause of the landslide.

Azhari Ahmad, who is Mineral and Geoscience Department (JMG) director for Perlis, Kedah and Penang, said the finding was made based on its inspection and monitoring since Saturday.

“The JMG team identified several factors that caused the landslide, resulting in all containers on the hill slope to slide down with the earth.

“The main factor that caused the landslide is the water flow from a stream near the slope and heavy rain since Friday morning caused the water to overflow,” he told reporters yesterday.

Azhari said the department had taken immediate measure by diverting the flow of water from the stream elsewhere to avoid worsening the situation, especially during the search and rescue (SAR) operation.

He said further inspection conducted at 7.30am yesterday found the water flow on the slope was lesser but the department would continue to monitor the situa­tion with equipment from the Special Malaysia Disaster Assistance and Rescue Team to ensure the safety of SAR personnel.

He said based on observation and inspection at the scene, the department found the location of the landslide to be at the concave slope which easily collected water.

“But we do not rule out the possibility of a follow-up landslide in the area due to the soil structure and there is still water flowing that can cause landslide.

“We have also advised the rescue team to stop operation immediately if it rains as it could cause another landslide,” he said.

Azhari said the department was assisting the rescue team in the SAR operation and did not rule out the possibility of it conducting further investigation to determine the ac­­tual cause of the landslide.

“We hope for fine weather and no rain so that the SAR operation can be continued until all the victims are found,” he said.

The landslide occurred at about 1.30pm last Friday.

The tragedy occurred following heavy rain in the state from Thurs­day afternoon until noon the following day, causing the landslide at the container and kongsi area at the Bukit Kukus paired road construction site.

Source: Bernama, Reports by LO TERN CHERN, N.TRISHA and R.SEKARAN

 

Related stories:

 

Zairil: Contractor to face action if accident due to negligence – Metro

 

 

Wake up and stop the landslides, state govt urged – Nation

 

Wake up and stop the landslides, state govt urged – Nation

 

 

DOSH: Builders told to stop work, but did not – Nation

 

CAP urges Penang govt to issue stop work order on hillside

 

October and November turning into ‘disaster season’

 

‘Put safety measures into place at construction sites’

Related post:

Precarious situation: The collapsed beams along Jalan Tun Sardon which fell and broke after being knocked down. https://www.thestar.c

Advertisements

PAC blamed Penang Island City Council (MBPP) for failing to enforce laws on hillside development


Becoming bald: A view of the clearing work seen at Bukit Relau which was visible from the Penang Bridge in November last year.

GEORGE TOWN: The Penang Public Accounts Committee (PAC) had faulted the Penang Island City Council (MBPP) for failing to monitor and enforce laws on hillside development in the state.

In its report on hill land development tabled on May 19, PAC said the lax monitoring not only resulted in unchecked hill clearing, but landowners were able to build houses, chalets, hotels and restaurants on Penang’s hill range.

“This situation happened because of MBPP’s failure to monitor and patrol hill land after notices were issued to landowners.

“This led to risks of soil erosion, landslides, mudslides, river sedimentation and disruptions to the surroundings,” it stated.

PAC’s report gained public attention after Penanti assemblyman Dr Norlela Ariffin brought it up in a dialogue session held by Penang NGOs and residents associations on flood and landslides on Sunday.

She told 200-odd members of the civil society that the report was tabled in the state assembly but never presented.

PAC stated that according to the state Audit Department, out of 31 illegal hill land clearing cases in 2015, four were in the Teluk Bahang water catchment area.

The committee, chaired by Bagan Dalam assemblyman A. Tanasekharan, visited nine of the cases on March 1.

It highlighted the Bukit Relau hill clearing case 410m above sea level and visible from Penang Bridge.

“Media reports and public comments should have been enough for MBPP and other authorities to take immediate action.

“Mitigation works on Bukit Relau have taken so long to be completed. The local authorities neither monitor the work frequently nor supply regular updates,” it added.

On illegal clearing that took place on Penang Hill, PAC expressed frustration that the actual dates and specific locations of the earthworks could not be determined because of the unsatisfactory records and monitoring.

“On Penang Hill, there was confusion on the existing agricultural plot and the new clearings.

“There are no definitions of allowable hill land agricultural works that involves digging,” it added.

PAC also objected to an earlier suggestion by the state Local Government Committee to exclude hill land earthworks related to agricultural activities from needing work permits.

Source: The Star by Arnold Loh

Related Links:

Massive works near Paya Terubong Paired Road raise fears

//players.brightcove.net/4405352761001/default_default/index.html?videoId=5631897984001

Related posts:

Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project.  Approximate Coordinates : 5°20’38.47″N,100°16’…
Council should not bow to development or political pressure, says city councilor, Khoo ‘Politicians should be ‘wakil rakyat’ and n…

Seeking solutions: Penang Forum member and soil expert Dr Kam Suan Pheng giving her views during the dialogue session themed ‘Penang Fl..

Speaking out: Penang Forum members protesting outside the CAP office in George Town. Don’t just make it about worker safety issues ..

https://youtu.be/QB45Q2_mOG0 Suspicious activity: A photo taken from Penang social  activist Anil Netto’s blog showing an active

(From left) Dr Kam will deliver a talk on ‘Understanding the Causes of Floods and Seeking Solutions. State Assemblymen expressing inter…
Wet, wet woes: (Above) Bukit Jambul is flooded once again after an evening downpour. Firemen installing a pump to draw floodwater…
Three slammed over finwall tragedy GEORGE TOWN: An incompetent engineer, a irresponsible one and a neglectful senior civil servant hav…
Image result for Penang Island City Council is No. 1 award

Image result for Penang Island City Council is No. 1 award  Fake Awards Scam for Penang Island City Council, Seberang Perai Municipal Council !   Dubious honours:Image result for Penang Island City Council is No. 1 award

Councillors ready to serve Penangites to make a difference?

Floods hit Bujkit Jambul & Hong Seng Estate in Penang


Wet, wet woes: (Above) Bukit Jambul is flooded once again after an evening downpour.

Firemen installing a pump to draw floodwaters from one of the affected houses on a slope in Hong Seng Estate, Mount Erskine.

GEORGE TOWN: A blocked underground drainage saw six houses located on a slope in Hong Seng Estate, Mount Erskine, flooded during an evening downpour.

Firemen and Civil Defence Force personnel had to install a water pump to draw out the rainwater which flooded some of the units to waist-level.

Rojak seller Tan Swee Hoe, 56, said she was shocked to see her kitchen and living room submerged in water at 7pm yesterday.

“I rushed home after receiving a call from a neighbour, saying my house is flooded.

“But I did not expect such a sight. I did not manage to move my furniture and electrical appliances to the upper floor, thus incurring several thousand ringgit in losses.

“I have been staying here for 17 years and this is the first time my house is flooded,” she said at her house.

Pulau Tikus assemblyman Yap Soo Huey said 17 people from five houses were affected while the sixth house was unoccupied.

She said the Fire and Rescue Department and the Civil Defence Force personnel moved in to install a 400m pipe to pump the water out from the house manually.

“The water is channelled to a nearby river and it may take a few hours if the weather is good,” she said, adding that the district office will evaluate the losses.

Late last month, seven houses in the estate were affected by soil erosion. A consultant engineer Datuk Lim Kok Khong had said the soil erosion was due to water seeping under the ground.

Penang Gerakan secretary H’ng Chee Wey urged the state government, with the aid of the experts, to look into the cause of the problems.

“The state government needs to ensure that the existing infrastructure, including the drainage system, can cope with the demand before it approve new development projects.

“We hope the local authorities can be proactive in the matter,” he added.

Rising waters also flooded the Bukit Jambul area, reducing traffic to a crawl.

Bayan Baru MP Sim Tze Tzin said a RM400,000 flood mitigation project started last month.

“The project will create a shortcut for the floodwater to be discharged directly to Sungai Nibong river instead of passing through Jalan Tun Dr Awang,” he said, adding that the project was expected to be completed at the end of next month.

Source: The Star by chong Kah Yuan

Related Links


 

Deluge brings chaos to northern states

Deluge brings chaos to northern states

Related posts:



Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project.  Approximate Coordinates : 5°20’38.47″N,100°16′

Council should not bow to development or political pressure, says city councilor, Khoo ‘Politicians should be ‘wakil rakyat’ and n…

Seeking solutions: Penang Forum member and soil expert Dr Kam Suan Pheng giving her views during the dialogue session themed ‘Penang Fl.

(From left) Dr Kam will deliver a talk on ‘Understanding the Causes of Floods and Seeking Solutions. State assemblymen expressing inter…
https://youtu.be/4qaOB1n5tgA GEORGE TOWN: The Penang Island City Council has  lodged a police report against the consultant of the aff…

Speaking out: Penang Forum members protesting outside the CAP office in George Town. Don’t just make it about worker safety issues ..

https://youtu.be/QB45Q2_mOG0 Suspicious activity: A photo taken from Penang social activist Anil Netto’s blog showing an active s..

Toray sets up new unit in Penang


Toray Malaysia Systems Solution Sdn Bhd
managing director Peter Chan (second right) speaking at a press
conference on Oct 17 after the official opening of Toray Malaysia
Systems Solution Sdn Bhd at the Setia SPICE Convention Centre in Penang.
Among those who were also present were Deputy Chief Minister II Dr P.
Ramasamy (middle) and Toray IS Division, Japan general manager Akihiro
Tada (first left)

 

Toray Malaysia Systems provides IT services

GEORGE TOWN: Toray Group (Malaysia), wholly-owned by Toray Industries Inc, Japan and one of the pioneers of Penang’s industrialisation programme, has expanded its business operations in Penang with the establishment of yet another company, namely Toray Malaysia Systems Solution Sdn Bhd (TMS).

TMS was established on May 2 with a RM5mil investment injected from Toray Japan.

It has offices at two locations in Penang, namely its head office at the Subterranean Penang International Convention and Exhibition Centre (Spice) and in Prai.

TMS managing director Peter Chan said the company, which is certified with MSC status by MDEC, provides global business services to its group of companies in Malaysia and abroad.

He said the company currently employs some 50 people and expects to increase the number to 100 within the next two to three years.

Chan said TMS provides full suite of information technology (IT) solutions and support for all aspects of business operations, ranging from planning and development to operation of information systems.

“These IT services include systems study, design, development, integration, deployment and maintenance, network infrastructure installation, IT helpdesk, systems administration support as well as IT consulting and IT research and development, according to customers’ stringent needs,” he added.

Chan said TMS is under the direct supervision of Toray Japan Information Systems Division.

“Backed by many years of information systems development experiences, technical know-how and skillful dedicated staff, TMS is set to contribute to Toray’s global business expansion as well as other related clients in Malaysia and the region.

“The head office at TMS Spice is equipped with the latest network infrastructure and IoT (Internet of Things) technology. It is designed to ensure that employees work in a conducive, healthy, happy, flexible working environment,” he said at TMS’ official opening at the Setia Spice Convention Centre recently.

Deputy Chief Minister II Dr P. Ramasamy, who was guest of honour at the event, said Penang recorded a total of RM5.3bil approved manufacturing investments from Japan from 2008 to 2016.

“I am also pleased to note that after the US and EU countries, Japanese investors make up the largest investments in Penang, making Japanese companies among the top FDI contributors to the Penang economy,” he added.

Source : The Star


Related posts:

Malaysia Toray Science Foundation (MTSF) – Winning ways with Science creations

IJM hill clearing & Trehaus construction damaged nearby houses since 2014 must be mitigated quickly!


Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project.
Approximate Coordinates : 5°20’38.47″N,100°16’52.82″E
Reported  in August 2016. Photos taken in November 2016 and 2014 by Penang Forum
PHW Report
See Video:

https://hillclearinginpenang.ushahidi.io/views/map

Sources: Penang Hills Watch (PHW) | Penang Forum

Hill clearing activity by IJM Trehaus Project

Clearing and construction for a condo and semi-detached housing
project, Trehaus, reported in http://anilnetto.com/ 26 Aug 2016. Photo
taken in 2014 …
IJM sign-boards
Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project.
Underground Pipe Culverts from IJM Trehaus site on the left and nearby pond on the right

Two invalid pipe culverts formed sinkholes at BJ Cove houses

Originally, there were two natural rivers/streams from the IJM Trehaus site and a nearby pond. No proper drainage system was implemented when housing development started, only two invalid hidden underground pipe culverts were built to channel the waters from the Bukit Jambul hill to Relau district. The invalid underground pipe culvert from the IJM Trehaus project directly  converged at BJ Cove houses from another invalid underground  pipe culvert from a nearby pond were burst, caused soil erosion, house slabs collapsed, multiple wall cracks, PBA water pipe burst, floods, sinkholes (by two pipe culverts converged in red) and damaged  to  BJ Cove houses due to blockages of waters whenever rains and because of lack of drainage system there.  The sinkhole which later converted into a manhole by IJM,  is a clear sign of soil erosion under the ground.

It is a common sense that waters from the natural rivers or streams are naturally running, seeped  through underground even the surface is covered by land-filled soil or with man made culverts.

Therefore, damages to houses were caused by severe soil erosion due to water movement under the road and buildings.

The following shows the invalid underground pipe culvert from the IJM Trehaus site behind BJ Cove houses at Lintang Bukit Jambul 1:

IJM Underground Pipe Culvert to BJ Cove houses 2018
Waters rising from the IJM Pipe Culvert behind BJ Cove houses 2018
Waters are flowing back from another pipe culvert at IJM site to BJ Cove houses 2018
IJM Underground Pipe Culvert at bottom to BJ Cove houses 2018
IJM modifying/constructing their underground pipe Culvert in 2014 to BJ Cove Houses
IJM modifying/constructing their underground pipe Culvert in 2014 to BJ Cove Houses

IJM Underground Pipe Culvert to BJ Cove Houses 
IJM Drains
IJM Drain Waters go  to the underground Culvert
IJM Underground Pipe Culvert next to BJ Cove Houses
The above and below show the bottoms of  IJM underground pipe culvert 

Waters gushing down from IJM Trehaus site to BJ Cove houses:

Waters flow from IJM Trehaus to BJ Cove houses

Waters gushing down from IJM Trehaus site to BJ Cove houses

Waters from IJM site stucked at behind BJ Cove houses

The nearby pond besides IJM Trehaus site:

IJM Hill cutting and hill Clearing 2014

Serious Drainage Issues

The Department of Irrigation and Drainage (DID or JPS) has just started in September 2017 constructing the drain from the pond to divert waters:
A drain under construction by JPS to divert waters from the nearby pond
Drain waters flow plan under construction by JPS to divert waters from the nearby pond

Letter from Penang Dept of Irrigation and Drainage (DID or JPS) in 2015 blamed IJM  failure to comply with sedement control plan (ESCP) when its Trehaus started in 2014.

Clearly, the underground pipe culverts leaked and waters seeped through the
ground and multiple cracks,  as it did not happen immediately but over a period of time!

Developers dishonored directives/letters issued by Penang City Council (MBPP – Majlis Perbandaran Pulau Pinang) in 2015 to rectify the damaged house

Developers have not completed their committments to rectify the damages despite  acknowledged their liability as per letters from Worldwide Venture Sdn Bhd, an subsidiary of IJM Land since 2014!

Despite the underground pipe culverts declared invalid by JPS and the Penang City Council’s (Majlis Perbandaran Pulau Pinang, i.e. MBPP) issued stop work
orders directing the developers, Worldwide Venture Sdn Bhd, a subsidiary of IJM Land to rectify the damages within 1 and 2 weeks time since 2015 (as per the above attached letters), the multiple wall cracks, slabs collapsed, PBA water pipes
burst, leakage charges, damaging ceiling, electrical DB board, and tiles
fallen, broken/popped up,  are still pending settlement and remedial works to be carried out by parties
responsible for the damages since 2014 !!

IJM Land only started in December 2017 constructing new drainage to divert waters from Trehaus Site to the pond and underground pipe culverts:

Pictures show IJM only started in December 2017 constructing drainage system to divert waters to the nearby pond and underground pipe culverts
Waters are flowing back to the pond during heavy rain 2018
Waters from IJM site overflown to the pond 2018
For waters to flow out smoothly, the pond must level up with more soils, 2018
Waters in the pond gone up during heavy rain 2018 – must build a wall  to prevent waters from seeping thru houses.
Waters cannot move out smoothly due to obstructions which are being removed by a man  2018
 

It is important that the pond should be made a dried pond instead of existing wet pond on the following reasons:

i) The area was originally a natural river/stream where waters will still be naturally running, seeped through underground even when the  underground culverts are to be closed/abandoned later.

ii) More waters were being diverted from the IJM site to their underground pipe  culvert and to BJ Cove houses.

iii) Now, drain waters from IJM site are being channeled back to IJM pipe culvert to BJ Cove houses at Lintang Bukit Jambul 1 where a manhole next to house no. 20 constructed by IJM is not closed despite it has been declared invalid and illegal by JPS!  This poses concerns to residents at BJ  Cove houses.

c
IJM Drain water Pipe Culvert Site to BJ Cove houses
IJM Drain water Pipe Culvert Site to BJ Cove houses
Waters stuck behind BJ Cove houses at IJM site 2018
IJM Drain  waters  gushing  down to pipe culvert
Sinkhole at house 20 is covered up by IJM’s underground pipe culvert from  IJM Trehaus

The damaged houses are still pending, not being completely rectified to date !

Damages appeared after IJM began construction works in 2014, like hill clearing, rock-blasting, piling and digging culvert at Trehaus site.  As a result, sinkholes appeared, floods, waters seepage through multiple cracks on the ground, walls, tiles fallen from roofs and popped up from the ground due to vibration from rock-blasting and piling works.

Sinkhole converted to manholes (2 in cycles) at BJ Cove houses are visible from the top of IJM Trehasu site

Pictures showing floods, sinkholes at Lintang Bukit Jambul 1, 11900 Penang,  damaged to BJ Cove houses, cracks, waters leakages seeped through the cracks, slabs collapsed, ceilings & tiles broken & fallen, electrical DB board explosion, etc caused by severe soil erosion due to water movement under the road and buildings. The underground pipe leaked and waters seeped through the cracks!

A big Sinkhole near BJ Cove house no. 20
IJM converted the sinkhole into a manhole waters from their underground pipe culvert at Trehaus
These are IJM Manhole converted from Sinkhole:
Sinkhole at house 20 is covered up by IJM’s underground pipe culvert from  IJM Trehaus
IJM converting the Sinkhole into Manhole next to  BJ Cove no. 20
Outside house drain and fence damaged by IJM during mitigation of Sinkhole
A big Sinkhole occurred due to invalid underground pipes culverts choked near house no. 20
Waters at the underground pipe culverts flown out from the house No. 20 to outside drain
Slabs collapsed due to cracks without compacted hardcore
Roof top Ceiling Board fallen due to strong vibration caused by IJM rock-blasting works 2014
Electric DB Board explored due to burst pipe waters seeped thru the wiring.


RM25k Kitchen damaged by concealed water pipes burst due to IJM Rock-blasting works 2015

Waters leaked from the burst pipes entered into Bedrooms

Multiple Cracks in Bedrooms 

Plumbers repaired the broken water pipes

Truth Be Told:

The
truths be told,  as echoed, reinforced and justified by recent events
in  Penang floods on 15th Sept 2017,  Landslides in Tanjung Bungah on 21
October 2017, the storm on Nov 4 & 5 2017, floods again on Jan 5,
2018, and the Huge ‘bleeding’ landslide in Tg Bungah hill  on May/June 2018  in related posts,

…. see more on links to following reports:

https://youtu.be/ooyXvqmxbvw GEORGE TOWN: Some 20 houses located on a slope in Hong Seng Estate in Mount Erskine were flooded due

Hills, landslides, floods and damaged houses …

Penang landslides & flooding are natural disasters man-made…  

Penang floods and landslides, looking beyound natural causes!

Penang landslide, whose faults?

Penang Paya Terubong Residents living under shadow of fear!

Penang landslide tragedy, why it happened?  

PAC blamed Penang Island City Council (MBPP) for failing to enforce laws on hillside development

We demand immediate enforcement & Actions:

1. The parties responsible must quickly without further delays, without condition to settle the claims and start the remedial works to the damaged houses, as both JPS has declared underground pipe culverts invalid and MBPP has  issued stop work orders directed the developers, Worldwide Venture Sdn Bhd, a subsidiary of IJM Land to rectify the damages within 1 and 2 weeks time since 2015!

2. Enforce IJM’s & MBPP’ Letters/Stop-work Orders (attached in above), and divert waters from the two invalid underground pipe  culverts deemed illegal at the IJM Trehaus site and nearby ponds which must be closed and grouted as a long term solution to the problems. 

3. Enforce a fresh cease and desist to Stop Work of IJM Trehaus  construction project until the structural damages to house at 20  Lintang Bukit Jambul 1, BJ Cove have been resolved and settled the claim for damages and distress caused by the fear and danger of living in the house, without further delays and their suffering more than four years since 2014.  Repairs and remedial works must start promptly as more damages and suffering will fellow!

4. Beef up the enforcement and accountability not just in  government agencies but also in professional bodies, like theBoard Of Engineers Malaysia (BEM),  the Institute of Engineers Malaysia (IEM), etc to uphold the professional ethics, integrity and standards, to ensure public safety of the buildings and people life.

5. The pond must be made a Dried pond for waters to flow out smoothly, because there was originally two natural rivers/streams in the area where waters will still be running/seeping through  naturally under the ground. 

 6. Now, drain waters from IJM site are being channeled back their underground pipe culvert flowing to BJ Cove houses at Lintang Bukit Jambul 1 where a manhole next to house no. 20 constructed by IJM  is not closed despite it has been declared invalid and illegal by JPS!  This is a great concern to residents at BJ  Cove houses. We want JPS and MPPP to close & grout the manhole promptly.

7. Damaged house owners firmly reserve all their rights to take all necessary legal steps against those responsible to any exclusion of
liability.

Findings from Penang Forum 

Dr Kam, a scientist, focused on expansion of impermeable surface area (caused by ill­ planned development and replacing natural ground cover such as hills, fields and trees that act as a water ­absorbing sponge) and soil erosion and landslides (caused by cutting and development in hill areas) as two factors that need special attention.

She quoted Datuk Kam U Tee, the Penang Water Authority general manager
(1973~­90), as having correctly explained the Penang floods of October 2008, as follows: the floods were caused by conversion of the Paya Terubong and Bayan Baru valleys into “concrete aprons that do not retain water. The water  immediately flows into streams causing flash floods even with moderate rainfall. Because of hill­cutting activities, the flowing water causes erosion of the slopes which carries mud and silt into the river beds”. ( The Star, Oct 24, 2008).


See more  ….

Credits: – Slides presented by Environmental, health and safety consultant
Aziz Noor, and scientist Dr Kam Suan Pheng at the Penang Forum event on Oct 29, 2017

See more ….

Practise true CAT for Sustainable Development

  • Penang government must provide a COMPETENT flood mitigation plan for the state starting with a comprehensive Drainage Master Plan Study and not slogan.

  • The Penang government has to be ACCOUNTABLE to the people and not private developers. In other words, ‘Politicians should be ‘wakil rakyat’ and not ‘wakil pemaju’. If certain waterways and  catchment areas have to be gazetted as permanent drainage and storage areas, then so be it.

  • The safety and well-being of the Rakyat has to come first.  In the
    interest of  TRANSPARENCY, Penang has to launch an inquiry into how the local council approved property developments on slopes without adequate slope protection.

 See more …

1. Wanted: Leaders who listen !

2. Sustainable Development in Penang

3. Call to reassess Penang hillside projects, councillor addresses full council meeting of MBPP

4. Penang landslide, whose faults?

Related:   

 

Include Penang Forum in panel probing Bukit Kukus landslide tragedy

 

 

  At Penang landslide memorial, group questions silence of PH MPs

 

Consultant, contractor of Bukit Kukus paired road project slapped with …

 

Risky building on hillslopes – Nation

 

In Malaysia, an island drowns in its own development

 https://news.mongabay.com/2018/07/in-malaysia-an-island-drowns-in-its-own-development/

Watch “Slope Stability” on YouTube

Penang MP rapped for asking for allocation while rejecting Budget …

KUALA LUMPUR: A Penang Opposition lawmaker was rapped for voting … Budget 2018 yet seeking an allocation for flood mitigation projects.

RM150mil for flood mitigation projects – The Star Online

A tempest flays the north

GEORGE TOWN: When the storm hit, everyone in the north prayed it would soon blow over.Penang flood: Precautionary power cuts in place as waters rise



Penang paralysed by floods – Nation

//players.brightcove.net/4405352761001/default_default/index.html?videoId=5635768537001

Irked residents to hold meeting with state representatives on Penang …

‘Bleeding’ landslide worries residents – Nation

Damaged houses to be repaired – Metro News

Rep: Redevelop village to solve recurring erosion – Metro News

Residents prefer affected houses to be torn down manually

Bruised in sinkhole fall at home – Nation

Penang CM must stop blaming past govt for problems

Cracks in homes force seven Penang families to flee – Nation

Here’s the proof — federal govt gave only RM443mil for flood mitigation

Former councillors claim Penang government abuse caused floods

PAS claims graft caused floods in Penang | Malaysia

Penang pays high price in storm havoc – Nation

Up to the chest in water, up to the neck with the excuses – Nation

Dept: Typhoon Doksuri caused erratic weather across Penang …

Rapid development in Penang root cause of massive flash floods …

Admit failure in solving floods and stop giving excuses, Penang govt told

Deluge brings chaos to northern states – Metro New

Penang mayor Maimunah quits job to accept UN post

Hiking trail in awful condition – Metro News

Clogged drains main cause of floods – Metro News

Narrow drains contribute to flooding

 The narrow drainage system which Chua claims results in flooding in the area.

Related posts:

A drone picture of the collapsed beams along Jalan Tun Sardon leading to Balik Pulau on the left while Jalan Paya Terubong on the ri…

Consultant gets show-cause letter for ‘overlooking hilltop stream’ GEORGE TOWN: The consultant of the Bukit Kukus Paired Road project…

Action taken over irregularities at Bukit Kukus paired road project Penang

Malaysia’s Penang Island has undergone massive development since the 1960s, a process that continues today with plans for transit and land-…

Huge landslide in Tg Bungah hill

Becoming bald: A view of the clearing work seen at Bukit Relau which was visible from the Penang Bridge in November last year. GEORGE..

Penang floods and landslides, looking beyound natural causes! Seeking solutions: Penang Forum member and soil expert Dr Kam Suan Pheng giving her views during the dialogue session themed ‘Penang Fl..

https://youtu.be/ooyXvqmxbvw GEORGE TOWN: Some 20 houses located on a slope in Hong Seng Estate in Mount Erskine were flooded due

How to measure a politician?

Use technology to learn more about them before casting your vote Cheah taking a wefie with Tanjung Bungah assemblyman Teh Yee Cheu (be…

 Wanted: Leaders who listen !

Turning a blind eye: The grumblings over exposed hills are growing louder but little is being done to rectify the situation   G…

  With the GE imminent, politicians are already snarling at each other, hoping to score points early. I love dogs. I’ve always had o…
It’s hard to deny when the effects of climate change are all around us  Andrew Sheng says that from increasingly intense hurricanes t…
Why did MBPP approve the Tanjung Bungah development project? Read more at https://www.malaysiakini.com/letters/399357#qbRd534yu1JfC551….
https://youtu.be/kslhytLg-Wc Hills, landslides and floods: What to do?   The mega floods in Penang which followed the landslide…
Choong (in white) surveying the deforested hillslope next to Majestic Heights. PENANG MCA has raised concerns about the safety of the r…
Wet, wet woes: (Above) Bukit Jambul is flooded once again after an evening downpour. Firemen installing a pump to draw floodwater…

Council should not bow to development or political pressure, says city councilor, Khoo ‘Politicians should be ‘wakil rakyat’ and n…
(From left) Dr Kam will deliver a talk on ‘Understanding the Causes of Floods and Seeking Solutions. State assemblymen expressing inter…
https://youtu.be/4qaOB1n5tgA GEORGE TOWN: The Penang Island City Council has lodged a police report against the consultant of the aff…

Speaking out: Penang Forum members protesting outside the CAP office in George Town. Don’t just make it about worker safety issues ..

https://youtu.be/QB45Q2_mOG0 Suspicious activity: A photo taken from Penang social activist Anil Netto’s blog showing an active s..

Some representatives of the 24 residents associations and management corporations showing messages urging the state to resolve the flood…
Our Environment is Our Life – YouTube THE year has barely started, and already we have so many reports of weather and climate-related e…
Sponge City: Solutions for China’s Thirsty & Flooded cities  China’s ‘sponge city’ projects may be worthwhile examp…

Getting titles right in the engineering field in Malaysia

Getting titles right in the engineering field in Malaysia ..

RECENTLY, the Institution of Engineers Malaysia (IEM) received an enquiry on the usage of the title “Engr.” for members of the institution. The  title “Ir” was first introduced by IEM in the early 1970s for both the graduate and corporate members of the Inst…Getting titles right in the engineering field in Malaysia rightwaystosuccess.blogspot.com

 2 structures collapse due to incompetent engineers and irresponsible officer of MPPP/MBPP

 Penang has acknowledged the Hills Clearing cases reported by Penang Forum

 

Penang Forum tells Chief Minister: the unmitigated disasters on hill projects 
Wall and awning collapsed in house near construction site
Penang Island City Council, MBPP councilor Dr Lim fed up change not happening in Penang

Penang Forum concerns over hill clearing and floods; the Declaration & Recommendation 

 Penang flood aftermath: design pump system needed to drain out water, fix funding snag …

  Long and winding road: This satellite picture from Google Earth Pro shows five planned interchanges of the Teluk Bahang-Tanjung Bun…

Humans Are Destroying the Environment PETALING JAYA: They are supposed to be guardians of the environment, and yet “certain enforcem…
LATELY, we have been seeing many photographs and a lot of video footage of handcuffed men and women in orange T-shirts bearing the wor…

IJM and Genting excluded from investments wealth fund due to severe environmental damage

Environmental issues: IJM and Genting have interests in palm oil
operations. Norwegian fund to call off investments on environmental
iss…

PETALING JAYA: Some RM40mil from the Skills
Development Fund Corp is believed to have been siphoned off by those
tasked with utilising it.

Taiwan developer detained over deadly quake building collapse …

The developer of a building in Taiwan that partially collapsed during an earthquake has been detained for negligent manslaughter with prosecutors saying the man was not licensed to oversee construction projects. The lower floors of the 12-storey Yun Tsui residential building which also housed a restaurant and hotel pancaked when a 6.4-magnitude quake struck the tourist hotspot of Hualien on February 6.  A total of 17 people died across the eastern coastal town, 14 of them in
the…

Getting titles right in the engineering field in Malaysia

 

Rage against hill road plan: We don’t want that road, says Penang residents


Long and winding road: This satellite picture from Google Earth Pro shows five planned interchanges of the Teluk Bahang-Tanjung Bungah paired road. The road starts at (1) Lembah Permai corner near Sri Vazhikattum Muniswarar shrine. The three interchanges in the middle are (2) at Jalan Sungai Emas, (3) at Persiaran Sungai Permai and (4) near Chin Farm Waterfall. The road ends (5) about 200m from the Teluk Bahang roundabout near the Toy Museum.

 

GEORGE TOWN: Alarm bells rang among Tanjung Bungah residents after they realised the proposed new road from Teluk Bahang to their neighbourhood entails de- forestation and construction on slopes with gradients steeper than 25 degrees.

They want the project scrapped and demand that the state government think of alternatives.

Through the Tanjung Bungah Residents Association (TBRA), 400 of them signed a petition against the project known as North Coastal Paired Road (NCPR).

TBRA chairman Meenakshi Raman said the environmental impact assessment (EIA) report showed that 3.34ha of gazetted forest reserves would be cleared for the road.

“Tracts of the Teluk Bahang Forest Reserve and Bukit Kerajaan Forest Reserve will be deforested. How can this be allowed?

“These reserves are gazetted as water catchment areas too,” she said in a press conference at the Tanjung Bungah market yesterday.

She said the EIA report revealed that 46% of the proposed road would be on slopes with gradients higher than 25 degrees.

“The EIA is clear that slope instability risks will be high. Mitigation measures are suggested but haven’t we learned enough about Penang’s development? Landslides occur often here,” she said.

The residents urged the Depart-ment of Environment (DoE) in writing not to approve the EIA. A copy of the letter was forwarded to Chief Minister Lim Guan Eng on Aug 21.

The NCPR is a 10.53km four-lane road from near SK Teluk Bahang until the L-shaped bend of Lembah Permai at Sri Vazhikattum Munis-warar shrine.

This is part of the Penang Transport Master Plan (PTMP) and is under the purview of Consortium Zenith Construction.

It is one of three new roads planned as the traffic dispersal system of the Penang Undersea Tunnel project.

Residents are also confounded by the cost.

Meenakshi said that in 2011, the estimated construction and land acquisition cost of the NCPR was expected at RM1bil.

She said the EIA stated that at an average speed of 70kph, motorists would save 14 minutes of travel time compared with the current coastal road.

“Spending such a huge amount to save 14 minutes is a colossal waste of public resources,” she added.

She felt that the EIA should have included a cost-to-benefit analysis.

“For RM1bil, can’t we think of other alternatives to the traffic problem?”

In response, state exco member Lim Hock Seng clarified that the clearing of the forest reserves was studied in the EIA as a requirement but the state was planning to avoid forest clearing.

“The first phase of NCPR is from Batu Ferringhi to Tanjung Bungah. That is the most urgent.

“The Teluk Bahang stretch, where the forest reserves are, won’t be built so soon.

“We do plan to continue examining alternatives to avoid deforestation.”

Lim said the main road in Batu Ferringhi could not “take it anymore during the holiday season” and the NCPR was vital to relieve traffic jams in the area.

Also, he said SRS Consortium, the state’s PTMP project delivery partner, was planning a viaduct from Lembah Permai to Seri Tanjung Pinang.

“So we are not dumping traffic or leaving a bottleneck at the Vale of Tempe Road with the NCPR.

“Motorists can choose between the winding coastal road or the NCPR depending on where they are going.

“This project will help reduce traffic,” he said.

Meenakshi also expressed shock that the EIA stated that NCPR would have 10 proposed interchanges.

But Lim and also Consortium Zenith chairman Datuk Zarul Ahmad Mohd Zulkifli said there would be only three interchanges in the middle of the road.

“They will be between Teluk Bahang and Tanjung Bungah, in Jalan Sungai Emas, Persiaran Sungai Permai and near Chin Farm Waterfall,” said Zarul Ahmad.

Penang Water Supply Corporation chief executive officer Datuk Jaseni Maidinsa gave an assurance that the NCPR’s route would not affect water catchment because the road would be downhill of Teluk Bahang Dam or any other reservoir.

Source: The Star by Arnold Loh

Call to scrap proposed road



Troubled spot: Aerial view of Jalan Lembah Permai in Tanjung Bungah, where the North Coastal Paired Road from Teluk Bahang will end in the L-shaped bend of the road. 

GEORGE TOWN: Tanjung Bungah residents want the proposed new road from Teluk Bahang to their neighbourhood scrapped after realising it entails deforestation and construction on slopes with gradients steeper than 25 degree.

Through the Tanjung Bungah Residents Association (TBRA), 400 of them signed a petition against the North Coastal Paired Road (NCPR).

TBRA chairman Meenakshi Raman said the environmental impact assessment (EIA) showed that 3.34ha of gazetted forest reserve will be cleared for the road.

“Tracts of the Teluk Bahang Forest Reserve and Bukit Kerajaan Forest Reserve will be deforested. How can this be allowed?” Meenakshi said during a press conference at the Tanjung Bungah market yesterday.

She said the EIA revealed that 46% of the proposed road would be on slopes with gradients higher than 25 degrees.

“The EIA is clear that slope instability risks will be high. Mitigation measures are suggested, but haven’t we learnt enough about Penang’s development? The island is sensitive to landslides,” she said.

The residents urged the Department of Environment (DoE) in writing not to approve the EIA. A copy of the letter was also forwarded to Chief Minister Lim Guan Eng on Aug 21.

The NCPR is a 10.53km four-lane road that is part of the Penang Transport Master Plan and is under the purview of Consortium Zenith Construction. It is part of the traffic dispersal system of the Penang Undersea Tunnel project.

The residents are also confounded by the cost. Meenakshi said in 2011, the estimated construction cost and land acquisition cost of the NCPR was RM1bil.

She felt the EIA should have included a cost-to-benefit analysis and “for RM1bil, can’t we think of other alternatives to the traffic problem?”

In response, state exco member Lim Hock Seng clarified that the clearing of the forest reserves was studied in the EIA as a requirement, but the state is planning to avoid it.

“The first phase of NCPR is from Batu Ferringhi to Tanjung Bungah. The Teluk Bahang stretch, where the forest reserves are, won’t happen so soon.

“Although it is studied in the EIA, we do plan to continue examining alternatives and avoid deforestation,” said Lim. – The Star

Related posts:

Stop denying the undeniable high engineering consultancy fees for 3 Penang roads, says minister

Dismayed over the exorbitant engineering consultancy fees, 4 times higher !

Behind BJ Cove houses at Lintang Bukit Jambul 1 is IJM Trehaus Project.  Approximate Coordinates : 5°20’38.47″N,100°16’52..

Stop denying the undeniable high engineering consultancy fees for 3 Penang roads, says minister



The works minister, Datuk Seri Fadillah Yosof says compared to what the JKR recently paid for pre-construction consulting fees for a project in Johor (RM19mil of pre-construction consulting cost represents 2.67% of RM718,570,500 for roads totalling 30km in length), the Penang government’s consultancy fees for the three roads project is exorbitant to the total RM220mil pre-construction fees that was already fully paid by the Penang government, which represented 11.06% of the RM1.99bil construction cost for the three roads totalling 20km in length and has yet to start construction despite a three-and-a-half-year delay.”

PETALING JAYA: The Penang government has been urged to “stop denying the undeniable” over the exorbitant consultancy fees for the three roads project.

Works Minister Fadillah Yusof said the Public Works Depart­­ment (JKR) recently paid RM19 million in total for pre-construction consulting fees for a paired road highway project in Jo­­hor.

He compared this with the exorbitant consultancy fees for the three roads project in Penang.

“The fees comprise all required services and include the fees for all surveys, soil investigation, preliminary environmental impact assessment and all civil, structural, electrical and mechanical designs,” The Star quoted Fadillah as saying.

He said the RM19 million of pre-construction consulting cost represents 2.67% of RM718,570,500 for roads totalling 30km in length.

He added that in accordance with the Board of Engineers Malaysia’s (BEM) guidelines, not all of the fees for the project were paid before construction began as a quarter of the payment was withheld for the tendering and construction stages.

“Compare this to the total RM220 million pre-construction fees that was already fully paid by the Penang government, which represented 11.06% of the RM1.99 billion construction cost for the three roads totalling 20km in length and has yet to start construction despite a three-and-a-half-year delay,” Fadillah said.

The three paired roads are meant to be the traffic dispersal system of Penang’s proposed undersea tunnel project.

The cost of the consultation fees for the three paired roads has been a point of contention between the state and federal government, whereby the latter says that the Penang government has significantly overpaid the fees.

The Penang government has maintained that the fees paid is not excessive. – FMT news, The Star

Related Links:

Stop denying the undeniable, says Fadillah – Nation

PCM lodges report over Penang undersea tunnel project – Nation …

Party plans to renew MACC report on Penang undersea tunnel project …

BNSC: Firm given Penang Tunnel project ‘undercapitalised’ – Nation …

Penang Undersea Tunnel – Wikipedia

CM: Penang undersea tunnel feasibility study can’t proceed | Free …

Bumpy road ahead for CZBUCG’s RM6.3b project – The Edge Property

Auditors qualify opinion on accounts of firm tasked with Penang tunnel …

Gerakan questions ‘high profits’ of tunnel feasibility study contractor …

PDF]PENANG MAJOR PROJECTS PRESENTATION – ENGLISH …

Making the corrupt fear whistleblowers, not the other way !

 

Related post:

Dismayed over the exorbitant engineering consultancy fees, 4 times higher !

%d bloggers like this: